Understanding Regional Priority Credits in LEED
Here are some sample questions to test your knowledge of LEED's Regional Priority credits:
Regional Priority Credit Details: Which statement is NOT accurate regarding Regional Priority credits?
- Regional Priority credits are listed by zip code on the USGBC website.
- Regional Priority credits are not new credits; they are bonus points for achieving existing LEED credits.
- Regional Priority credits are also known as exemplary performance credits.
- Six Regional Priority credits are available for each zip code.
- A project can earn a maximum of four Regional Priority credits.
Design Review Submittals: A project team has submitted an initial submittal for design review. What can be expected in response to this design phase submittal? (Choose two)
- The USGBC will not formally rule on a design submittal.
- The USGBC will formally rule on each submitted credit as Achieved or Denied.
- The USGBC will make recommendations regarding additional credits to apply for.
- The USGBC will only rule on credits relating to Site Selection.
- The USGBC will formally rule on each submitted credit as Anticipated, Pending, or Denied.
Project Information Forms: Are all project information forms designated as 'approved' or 'not approved'?
Existing Building CFC Phase-Out: An owner of an existing building has agreed to phase out CFC-based refrigerants to meet LEED minimum requirements. What is required of this CFC phase-out plan? (Choose two)
- CFCs must be 100% phased out within 5 years.
- CFCs must be 100% phased out within 10 years.
- CFCs must be 100% phased out within 20 years.
- During the phase-out plan, CFC-based refrigerant annual leakage must be reduced to 5% or less.
- During the phase-out plan, CFC-based refrigerant annual leakage must be reduced to 10% or less.
- During the phase-out plan, CFC-based refrigerant annual leakage must be reduced to 20% or less.
Earning Regional Priority Credits: How can a project earn Regional Priority credits?
- By satisfying the requirements for the Regional Materials credit.
- By using only local vendors.
- By addressing geographically specific environmental priorities.
- By satisfying LEED credits labeled as a priority by the state the project is in.
Credit Interpretation Requests (CIRs): Which of the following statements are true about submitting a Credit Interpretation Request (CIR)? (Choose three)
- CIRs should be submitted using LEED Online.
- It is helpful to submit drawings or attachments that help explain the question.
- Each CIR must only be for one credit or prerequisite.
- CIRs should be in a letter format.
- CIRs shall not contain in excess of 600 words.
Key Takeaways:
- Regional Priority Credits: These credits offer bonus points for addressing local environmental concerns.
- LEED Online: Submitting CIRs is done through the LEED Online platform.
- Phase-Out Plans: CFC phase-out plans have specific timelines and leakage reduction requirements.
- Geographic Focus: Regional Priority credits emphasize addressing priorities specific to the project's location.
- Design Review: Understand the process and expectations during the design review phase.